top of page

Building Statistics

PROJECT //  01

Project team

Owner:

Confidential*

General Contractor:

Turner Construction

http://www.turnerconstruction.com/

Construction Manager:

Turner Construction​

http://www.turnerconstruction.com/

Architects:

Marion Weiss and Michael Manfredi​

http://www.weissmanfredi.com/

Engineers:

Thornton Tomasetti (Structural Engineers)

http://www.thorntontomasetti.com/

Jaros, Baum & Bolles (M/E/P/FP)

http://www.jbb.com/

 

Heintges (Glazing)

http://www.heintges.com/

Renfro Design Group (Lighting)

http://www.renfrodesign.com/

General Building Data

Building Name  ǀ Weiler House

Location and Site  ǀ  San Francisco, CA

Building Occupant Name   ǀ   Weiler Colocation House

Occupancy or Function Type  ǀ  Business/Assembly 

Overall Building Size  ǀ   188,603 SF

Number of Stories   ǀ    6 stories above grade;  7 total levels

Primary Project Team  ǀ   Weiler House

Turner Construction, Weiss/Manfredi, 

Tomasetti, Baum&Bolles(B&B), Heintges, 

Renfro Design

Dates of Construction  ǀ   May 2015 – Summer 2017

Actual Cost Information  ǀ  Contract Value: Core and Shell - $100 Million

Project Delivery Method   ǀ  Design – Bid– Build

architecture

Design and Fuctional Components

 This co-location center is designed to combine student research and companies in industry to create innovation in new products and technologies. The mixed use building contains a 2 story atrium located in the main entrance lobby shown in Figure 1. and a shaded slanted skylight . Allowing high natural daylight, low emissivity and a reduction in lighting operation. A centralized stairway is used to incorporate seating and natural egress to the second floor. Leading to tenant fit out spaces that surround the core elevator.
zoning
Utilizing group 6 (Commercial) and group 3 (Community Facility) zoning. The project has a zoning area of 188,603 SF which excludes the below grade level and the MEP chase on 1-6. 
Figure 1. Interior Lobby 
Applicable codes

2014 San Francisco Building Code

2014 San Francisco Fire Code

Figure 4. Green Roof System
Figure 3. Exterior Elevation
Figure 2. Exterior Render

Building Envelope

Weiler House features a curtain wall system with aluminum mullions, aluminum cladding and  aluminum soffit edges. Figure 2 and 3. displays the aluminum cladding.The aluminum cladding is located on the inner and outer wing portions of the building while, the the curtain wall system remains the most frontward and backward facing. Each curtain wall panel consists of insulated low E glazing with varying fritted glazing patterns.
The Roofing material is a TPO membrane with concrete pavers laid above. The Typical buildup of this roof consists of a flashing layer, two layers of 2" rigid insulation, an air layer, root barrier, filter fabric, and pavers on jack stands. The roof system incorporates a green roof which, can lead to better thermal insulation and water management savings. Using the rainwater collected to provide irrigation and in some cases can be used as gray water saving. This can ultimately require less work load on mechanical and plumbing systems. The green roof is similar in build, the filter fabric is replaced with a drainage mat and vegetation above. A unique aspect is clearly shown in Figure 4. and is a functional roof feature. The solar canopy provides a shelter from rain  and provides additional electricity due to photo voltaic panels. Meshing the two functions of rain protection and electricity generation.

Sustainability Features

Sustainable features include a rooftop solar array system, generating additional electricity and lowering electrical usage. Followed by a bathtub foundation design containing a deep basin and high walls to keep water out. Next, a green roof water management and storm water capture. This utilizes the storm water for reuse in gray water systems, as well as efficient fixtures to maximize savings. Lastly, natural daylight. By using large curtain wall panels, daylight can be maximized, reducing lighting usage and ultimately improving occupant performance.
Primary systems
COnstruction
Weiler House is part of a 30 year campus renewal plan, located on 2.5 acre plot of land. Turner construction was appointed the general contractor for the  construction of the project and possess a Design-Bid Build  with Weiss/Manfredi for design of the building. Located at a undisclosed location, it contains two main roads on adjacent sides of the site. Logistics of the site are important due to four projects occurring simultaneously. Construction  of Weiler House will utilize a single 40 ton hydraulic crane, with boom length that is able to reach  Weiler's seven story height. The  curtain wall facade is a critical path item, and panels are a  critical long lead item required for the project. Overall, the project is scheduled to  meet the  project closeout  on March 3, 2017.
Structural
The structural system for Weiler House is composed of structural steel framing and composite steel deck. With the main superstructure consisting of structural steel columns, beams, and trusses that not only support  each floor, but also support a  2 story lobby atrium. Concrete slabs at the main lobby are 2 ways slabs, depressed 3". Floors above are   5" composite  steel deck, with lateral bracing at the main face that support the braced framed curtain wall system. The roof is a  sloped reinforced concrete slab system with drainage penetrations. Framing for each floor are standard wide flange beams that vary in length, from 4'-40'.
Mechanical
Mechanical systems are located at numerous floors throughout the building. At the cellar level there are 5  mechanical rooms. A main garage and building mechanical room, fire tank/ pump room, water meter room, and fuel tank/pump room. Each subsequent floor has at lest one mechanical leading to the roof. The roof houses a stainless steel 255,200 CFM cooling tower with a  chiller in the cellar level mechanical room. This leads to a water cooled air-conditioning system with inlet return air acoustical plenums at all levels above the cellar level.
electrical
A  utility transformer connects to the main switchboard, located at the penthouse at 3000 Amps. Traveling to 10 transformers throughout ranging from 30  KVA- 70 KVA. This leads to panel boards located on 1, 3, 6 floors providing  electricity for light fixtures and receptacles. At the roof level a solar canopy houses Photo-voltaic panels, providing additional energy through sun light.
lighting
Lighting is composed of Recessed LED down-lighting for the lobby, atrium, and elevator  skylights. Using LEDs  will minimize energy consumption and serve  as a decorative fixture as well. Occupancy sensors are wall mounted  according  to spaces and  are automated for main community spaces such as the lobby atrium. Lighting is controlled within spaces by a main control switch, giving the user defined lighting schemes. These main  lobby system will be programmed on a 12 hour low energy consumption schedule to reduce lighting load.
bottom of page